Can Your Project Continue After Liquidation?

Authored by Kelly Simon

Published 2 November 2026

In this article

Liquidation can disrupt a construction project at every level of the contractual chain. Whether the company in liquidation sits upstream as a principal or head contractor, or downstream as a contractor or subcontractor, the appointment of a liquidator can quickly affect funding, performance, security, site control, and the project’s prospects of completion.

Unlike some other forms of external administration, liquidation generally brings the company’s operations to an end. A liquidator takes control of the company, collects and sells its assets, investigates its affairs, and distributes available funds to creditors according to the applicable priorities. For an ongoing construction project, the company in liquidation may no longer have the funding, authority, personnel, or licensing needed to continue performing its contractual obligations.

The remaining project participants must assess whether the project can continue and, if it cannot continue with the company in liquidation, identify the contractual rights available to them.

Start with the contract

The contract will usually determine the options available when a project participant enters liquidation.

Well-drafted construction contracts commonly address insolvency events and set out the rights that arise when one party enters liquidation. Depending on the contract, these rights may include the ability to:

  • terminate the contract;
  • suspend performance;
  • take the remaining works out of the contractor’s hands;
  • engage others to complete the works;
  • call on bank guarantees or other security;
  • retain money otherwise payable;
  • exercise set-off rights; and
  • recover additional completion costs.

Parties must still exercise these rights in accordance with the contract. Before issuing a notice, terminating the contract, or taking over the works, they should confirm any preconditions, notice requirements, timeframes, and procedural steps that apply.

A party that rushes to terminate without following the contractual process may create a separate dispute about whether the termination was valid. That dispute can increase the cost of responding to the liquidation and delay the appointment of a replacement contractor.

The contract should also identify whether a party can request financial information where concerns arise about another participant’s solvency. If the contract includes that right, obtaining information before a formal insolvency appointment may help the principal or contractor assess payment exposure, security, and whether the project can continue.

Can the project continue?

Whether the project can continue will depend on the insolvent company’s role, the availability of funding, any applicable licensing requirements, and the liquidator’s intended course of action.

Liquidation usually limits the company’s ability to continue trading. The liquidator focuses on winding up the company, recovering its assets, and distributing funds to creditors. Continuing a construction project may not support that purpose, particularly if the company cannot pay its employees, subcontractors, suppliers, or other project expenses.

Licensing may also prevent the company from continuing its work. In Queensland, for example, liquidation may result in the immediate cancellation of a construction company’s licence. If the company no longer holds the licence required to perform the work, it cannot continue, even where the other project participants would prefer to avoid the cost and delay of replacement.

Where continuation appears possible, the remaining parties should confirm directly with the liquidator who will fund and direct the work, whether employees, subcontractors, and suppliers will continue to be paid, whether the liquidator intends to perform the existing contract, and who will accept responsibility for liabilities incurred after the liquidation began.

Project participants should not assume that the liquidator will continue the company’s operations or honour its existing contractual commitments.

What happens if the insolvency event occurs upstream?

An upstream insolvency event may involve the principal, developer, or head contractor.

For contractors and subcontractors further down the contractual chain, the main issue will often be whether project funding remains available. If the upstream party can no longer fund the project, there may be no reliable source of payment for work already performed or work performed after the liquidation.

Contractors should promptly establish:

  • whether the project will continue;
  • who will fund any continuing work;
  • whether outstanding payment claims will be paid;
  • whether a replacement entity intends to take over the project;
  • what will happen to security provided upstream;
  • whether the existing contracts will be novated; and
  • who will remain responsible for liabilities that arose before the replacement arrangement.

A new developer, financier, or principal may decide to complete the project and retain the existing delivery team. In that situation, the parties may explore a novation or replacement contract.

A novation will not resolve the project’s existing liabilities unless the parties address them expressly. The contractor must still consider whether the new party accepts responsibility for outstanding payments, existing claims, security, defects, variations, extensions of time, and other liabilities that arose under the original arrangement.

The contractor should also investigate what has happened to retention money. If the insolvent principal has already used or dissipated the retention, the contractor may struggle to recover it. Similarly, any bank guarantee or other security provided upstream may remain exposed to a call.

If no replacement party agrees to fund the project, the contractor may need to demobilise, protect the site, limit further costs, and pursue its claim through the liquidation. Recovery may prove difficult, particularly where significant unpaid amounts have accumulated and the insolvent company has few remaining assets.

What happens if the insolvency event occurs downstream?

A downstream insolvency event commonly involves a contractor or subcontractor that can no longer complete its scope of work.

The upstream party will usually need to decide whether to terminate the contract or take the remaining works out of the insolvent party’s hands. That decision will depend on the contract, the stage of the works, the value of outstanding payments, the extent of any defects or delay, and the cost and urgency of engaging a replacement contractor.

Before exercising any contractual right, the upstream party should document:

  • the work completed to date;
  • incomplete work;
  • defects;
  • materials, plant, and equipment on site;
  • outstanding subcontractor and supplier claims;
  • available design documents and project records;
  • the anticipated delay; and
  • the estimated cost of completing the works.

This information will support decisions about replacement procurement and may also form the basis of a set-off or claim against the insolvent company.

If money remains payable for work performed before liquidation, the liquidator may seek payment. The upstream party should first assess whether the contract permits it to set off completion costs, defect rectification costs, delay costs, or other claims against that amount.

The party must support any set-off with credible evidence. A liquidator may require proof of the costs actually incurred to complete or rectify the works. General estimates, unsupported allowances, or inflated completion costs may not withstand scrutiny.

The project team should therefore retain quotations, invoices, site records, photographs, programmes, defect lists, correspondence, and evidence of payments made to replacement contractors.

Retentions, bank guarantees, and payments

Retentions and bank guarantees may provide funds or leverage to address the consequences of a contractor or subcontractor entering liquidation.

The upstream party should review whether it can retain retention monies, call on a bank guarantee, or otherwise use security to meet the cost of completing the works. It should also check the contractual conditions governing recourse and comply with any required notices.

Parties should take care before agreeing to an early release of security where signs of financial distress have emerged. Once security has been released, it may prove impossible to recover equivalent protection after liquidation.

The same caution applies to payments. Where the contract permits, the paying party should consider withholding amounts that may be required to meet completion costs, defects, or other claims. It should not pay more than the contract requires merely because the liquidator applies pressure.

However, the liquidation itself does not create an unrestricted right to withhold payment. Any withholding or set-off must have a proper contractual and evidentiary basis. The appropriate response depends on the terms of the contract, the status of the account, and the value of any genuine offsetting claims.

Act early and preserve evidence

Signs of financial distress often become known within the construction industry before a formal insolvency appointment. Parties should not act solely on rumours, but credible warning signs may justify closer review of the project’s financial and contractual position.

Before liquidation occurs, practical steps may include:

  • reviewing the contract’s insolvency, termination, takeover, payment, and security provisions;
  • confirming the status of retention and the expiry dates of any bank guarantees;
  • reconciling the project account;
  • requesting financial information where the contract permits; and
  • documenting completed work, defects, materials, plant, and progress.

Once a liquidator has been appointed, the project team should secure the site, document the condition and status of the works, identify materials and plant, and preserve access to designs, programmes, records, and correspondence. This information will assist with replacement procurement, claims against security, set-off calculations, and any proof of debt lodged in the liquidation.

Parties that review their rights promptly, preserve security, control payments in accordance with the contract, and maintain detailed project records will be better placed to complete the works and manage the resulting financial exposure.

Have a question?

If you’re unsure how this applies to you, feel free to send us a message.

Related Articles

How can we help?

Whether you're facing an issue or planning ahead, we’re here to help you move forward. Share a few details using the form to get started.