You have done the work, calculated what you are owed, and prepared your monthly claim. Before you send it, check the reference date, the contracting entity, and the service requirements, along with the elements every payment claim must contain.
Under Queensland’s security of payment regime, those details can determine whether you are able to use the statutory process to recover payment. Even where you have a strong contractual entitlement, an error in preparing or delivering the claim can put that recovery option at risk.
The Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act) provides a fast, interim process for recovering progress payments. Here is what construction managers, contract administrators, and legal teams should check before issuing a claim.
Start with your reference date
Before preparing the claim, confirm that Chapter 3 of the BIF Act applies to your contract and work. Then identify the reference date you intend to use.
A reference date is the date from which you become entitled to a progress payment for construction work you have performed, or related goods and services you have supplied, under the contract.
Check when your contract allows you to make a payment claim. If the contract does not address reference dates, the BIF Act provides them: the last day of the month in which you first performed the work or supplied the goods or services, and the last day of each later month.
If the contract has ended, check whether it preserves reference dates after termination. Where it does not, or seeks to prevent a reference date surviving, the BIF Act provides a final reference date on the termination date.
Before issuing the claim, confirm that your reference date has arisen and that it hasn’t already been used up by a previous payment claim.
Cover the four essentials
Your payment claim must:
- Go to the person who is or may be liable to pay under the construction contract.
- Identify the construction work or related goods and services you are claiming for.
- State the amount you claim.
- Request payment of that amount.
You do not need to use a prescribed form or give the document a particular heading. An ordinary invoice can operate as a payment claim if it meets the requirements.
For claimants, that means checking the substance of the document before sending it. For respondents, it means reviewing incoming invoices promptly rather than assuming only a document labelled “BIF Act payment claim” requires attention.
Check who actually owes the money
The person you deal with each day may not be the party responsible for payment.
You might submit assessments to a superintendent, discuss variations with a project manager, and receive correspondence bearing a corporate group’s branding. None of those arrangements necessarily identifies the contracting entity liable to pay you.
Check the executed contract and identify the correct respondent. Do not address the claim only to a superintendent, parent company, related entity, or trust name unless that is the liable contracting party.
You can copy other project contacts into the correspondence, but make sure you also give the claim to the correct respondent through an effective service method.
Follow the service requirements
Read the contract’s service provisions. They may permit email, Procore, Aconex, or another nominated method. Statutory service avenues may also apply.
Using a familiar project communication channel does not automatically establish that you have validly served the claim. An unauthorised method can lead to disputes about whether service occurred and when the respondent’s time to respond began.
Keep a complete copy of everything you served, along with evidence of delivery. If the claim is too large for email, work out the delivery method before the deadline. Do not assume that sending a link achieves service of every document stored behind it.
Show what you are claiming and how you calculated it
The respondent should be able to read your claim and understand both the work involved and the amount you seek.
Use descriptions that match the contract, and organise the claim by trade, variation, or milestone. Include relevant item numbers and document references so the recipient can connect each amount to the supporting records.
For example, a variation described only as “additional works” leaves several questions unanswered. What work did you perform? Who directed it? When did you carry it out? How did you calculate the price?
Answer those questions in the claim and its supporting documents rather than leaving the respondent to reconstruct the position.
Show previous payments, explain deductions, and reconcile the breakdown with the total. If you claim a percentage of an item, explain what that percentage applies to and how it produces the amount claimed.
This gives the respondent enough information to assess the claim and provides a clearer foundation if you later pursue adjudication.
Ask for payment directly
It is easy to assume that showing an amount owing is the same as asking for payment. Wording such as “amount due this claim”, however, may leave room for an argument about whether you have satisfied that requirement.
A direct request avoids the issue:
“The claimant requests payment of $500,000.”
The BIF Act treats a tax invoice as satisfying the request for payment requirement, but including an express request makes your intention clear.
Check that the amount you request matches the total in the claim and supporting calculations.
Be careful with drafts and revised claims
You can make only one payment claim for each reference date. Before issuing yours, check whether you have already sent a document that could qualify.
Calling something a “draft” does not necessarily stop it from operating as a payment claim. If you give it to the respondent and it otherwise meets the requirements, the respondent may argue that you have already used the reference date.
Keep internal review versions within your team until you approve the claim for issue. If you send it through multiple channels, use the same approved version each time.
Check how long you have to claim
For a claim other than a final payment claim, you must give it within the later of:
- the period your contract provides; or
- six months after you last performed the relevant construction work or supplied the related goods or services.
For a final payment claim, compare the contractual period, six months after completion of the work or supply, and 28 days after the end of the last defects liability period. Identify the latest applicable deadline.
Keep records of those dates as the project progresses. Before sending the claim, check them alongside the reference date and service requirements.
The takeaway
A final review should confirm who must receive the claim, what you are claiming, how you calculated it, and when and how you will deliver it. Resolving those issues before service helps preserve your recovery options if payment does not follow.
If you would like help preparing a payment claim or reviewing your team’s claim procedures, our construction team can assist.